Water supply system design (WSSD) for 8-HC water supply purpose
Study time (project duration):- 20-days, March-2019
- Expected-1 :- 3-water well system design
- Design of 1.5_2km for each
- Estimated Discharge 3-4l/sec
- For 3-HC & nearby community
- Expected-2:- 6-Spring development system design
- Design of 0.5_2km for each
- Estimated Discharge 0.2-3l/sec
- For 6-HC & nearby community